25 October–- Refine pilot procedure

1 November–– Half of relevant research completed, reviewable draft of (pilot) methods section

8 November–– Final related works/methods refined and Interface Prototype

15 November–– Interface Done

22 November–– Pilot (aim for N = 7) and revised procedure (if necessary) complete

29 November–– 3/4 of subjects run

6 December–– All subjects run/analysis attempted.

13 December–– Data analysis complete and results section written/Abstract

19 December-- Everything done