'''Week 3: 11/8 - 11/15''' | '''Week 3: 11/8 - 11/15''' | ||
: List of features / ideas to be implemented by the end of the 50-days | |||
: Interview report of other potential users | |||
'''Week 4: 11/15 - 11/22''' | '''Week 4: 11/15 - 11/22''' | ||
: Visualization tool prototype | |||
: Evaluation plan | |||
'''Week 5: 11/22 - 11/29''' | '''Week 5: 11/22 - 11/29''' | ||
: User feedback on the prototype | |||
: First feature implemented | |||
'''Week 6: 11/29 - 12/6''' | '''Week 6: 11/29 - 12/6''' | ||
: Second feature implemented | |||
'''Week 7: 12/6 - 12/13''' | '''Week 7: 12/6 - 12/13''' | ||
: Two-page abstract | |||
== Task Decomposition == | == Task Decomposition == | ||
Revision as of 21:07, 8 November 2011
Design & Evaluation of EEG Data Visualization Tool Based on Cognitive Task Analysis
Project Schedule
Week 1: 10/25 - 11/1
- Preliminary task decomposition (list and diagram)
- Refined related work section with related work on high dimensional data visualization
Week 2: 11/1 - 11/8
- Refined (hopefully final) task decomposition
- Complete related work section
- Feature list of the visualization tool
- Sketch of the interface of the visualization tool
Week 3: 11/8 - 11/15
- List of features / ideas to be implemented by the end of the 50-days
- Interview report of other potential users
Week 4: 11/15 - 11/22
- Visualization tool prototype
- Evaluation plan
Week 5: 11/22 - 11/29
- User feedback on the prototype
- First feature implemented
Week 6: 11/29 - 12/6
- Second feature implemented
Week 7: 12/6 - 12/13
- Two-page abstract