== Steve's Project Schedule == | == Steve's Project Schedule == | ||
'''Nov 1''' -- | '''Nov 1''' -- Filling out the paper: Abstract, related work and intro drafted; outlines for results and methods. Update on data and contact with Win. | ||
'''Nov 8''' -- | '''Nov 8''' -- Test MRIs (hopefully 10) collected and organized; evaluation protocol completed | ||
'''Nov 15''' -- | '''Nov 15''' -- Video captures of research assistants analyzing MRIs for QA (first session) | ||
'''Nov 22''' -- | '''Nov 22''' -- continued: Video captures of research assistants analyzing MRIs for QA (second session) | ||
'''Nov 29''' -- | '''Nov 29''' -- Coding of video captures completed; will share findings | ||
'''Dec 6''' -- | '''Dec 6''' -- Analysis of codings; figures for final paper created | ||
'''Dec 13''' -- Final draft, two-page extended abstract of research project | '''Dec 13''' -- Final draft, two-page extended abstract of research project | ||
Revision as of 19:49, 24 October 2011
Steve's Project Schedule
Nov 1 -- Filling out the paper: Abstract, related work and intro drafted; outlines for results and methods. Update on data and contact with Win.
Nov 8 -- Test MRIs (hopefully 10) collected and organized; evaluation protocol completed
Nov 15 -- Video captures of research assistants analyzing MRIs for QA (first session)
Nov 22 -- continued: Video captures of research assistants analyzing MRIs for QA (second session)
Nov 29 -- Coding of video captures completed; will share findings
Dec 6 -- Analysis of codings; figures for final paper created
Dec 13 -- Final draft, two-page extended abstract of research project